6. Stripping of formwork and transportation to the next site



We will be glad to see you on exhibition ANGA Cable 2009, which will take place 26 - 28 May in Cologne Fair Grounds, Hall 10.2, stand K48, Cologne, Germany
  1. Hold the concrete solidification time.
  2. Remove unfastened elements of casing and scaffolds.
  3. Set the bearing cramps on the opposite casing elements bundle; stretch the slings by crane (see pic. 11).
  4. СRemove the anchors and junctions between adjacent casing elements (see pic. 11).
    Attention! To speed up the works on moving of the casing elements by crane it is possible to remove most part of anchors before. Leave the number of anchors which provide vertical position and hold the casing from falling.
    Attention! It is strongly prohibited to tear away the casing elements bundle by means of crane. You should use special tools or wooden wedges for this means.
  5. Lift up the casing elements bundle and move it to the interim point or directly to the new installation site.
  6. Clean the paneling of casing from concrete remains (see Part 22).
  7. Hang up the casing element bundles with working scaffolds and supporting braces on the crane by means of the bearing cramps. Unfasten the supporting braces from ground.
  8. Lift up the casing elements bundle with working scaffolds and supporting braces and move it to the interim point or directly to the new installation site. Clean the paneling of casing from concrete remains (see pic. 12).
  9. Repeat works described in 6.2…6.8 necessary number of times.