1. Moving of the casing elements by means of transport hanger
- Offloading of piles from transport and moving of them on the construction site should be made using crane equipped with transport hanger (equipped with 4 round loops) (see pic.1).
- Tie round the pile from all four sides with four round loops for transportation (loops will not let to slide down to single element of casing).
- Spring support hub should be positioned under on the frame corners (hubs will not let the sling to slide off in case of bracing slackness).
Automatic adjustment of transport sling length contributes load trim. - Attaching and detaching of transport sling is made by one person.
Permissible total load is 2000 kg. - Moving of piles and separate elements of casing on small height should be made using four-point sling, 3,2 m long (see pic. 2)
Permissible total load is 2000 kg. - Fastening of transport bolt of four-point sling should be made in following way:
- to insert transport bolt to the frame slot up to the stop;
- transport bolt will be fixated by lifting of the load.
- During moving of the bundle of casing elements it is necessary to position two-sided cones between the elements of casing, which prevents element slipping.
Attention! Moving of the bundle of casing element and piles without two-sided cones is strongly prohibited!

Attention! Stripes holding the pile may break during the lift under high load.